ASME B31.3 vs B31.1
Process piping and power piping: two sections of the ASME B31 code
The short answer
ASME B31.3 covers process piping in refineries, chemical and gas plants, terminals and offshore topsides. ASME B31.1 covers power piping: power stations, industrial and institutional plants, geothermal heating, central and district heating and cooling, and the external piping of power boilers. On an oil and gas facility nearly all piping is B31.3. B31.1 usually appears only where the site has steam boilers or a power plant.
Side by side
| ASME B31.3 | ASME B31.1 | |
|---|---|---|
| What it is | Process Piping, one section of the ASME B31 Code for Pressure Piping | Power Piping, one section of the ASME B31 Code for Pressure Piping |
| Issued by | ASME | ASME |
| Typical plants | Refineries, chemical plants, gas processing plants, terminals and offshore topsides | Power stations, industrial and institutional plants, geothermal heating, and central and district heating and cooling |
| Typical services | Any fluid in the plant: hydrocarbons, chemicals, toxic fluids, steam, air and water | Steam, feedwater and condensate, and the water, oil, gas and air services of a power plant |
| Boilers | Power boilers and the boiler external piping that must meet B31.1 are excluded | Covers boiler external piping, which must also meet the BPVC Section I rules for documentation, inspection and stamping |
| How the rules are graded | By fluid service: Normal, Category D, Category M, Elevated Temperature, High Pressure and High Purity | Has no fluid service categories of the B31.3 kind |
| Stresses and examination | Its own allowable stresses and examination rules | Its own allowable stresses and examination rules, which differ from B31.3 |
| On oil and gas facilities | Process, utility, flare, drain and chemical injection piping | Steam boilers and their piping, and any power or cogeneration plant on the site |
| How they relate | Applies on the process side of a code break | Applies on the boiler and power side of that break |
A summary in our own words. Check the scope clauses of the current editions, and the project specification, for where each section applies.
When each one applies
The section follows the kind of plant and the job the piping does. Hydrocarbon, chemical and utility piping inside a process plant or on a platform topsides is ASME B31.3. Piping in a power station, a steam plant or a district heating scheme is ASME B31.1.
The B31 code makes the owner responsible for choosing the section that applies, and more than one section can apply to different parts of one installation. The choice is written into the piping specification, so designers and fabricators do not have to make it again for every line.
Using both on one site
A refinery or gas plant with its own steam boilers often uses both. The boiler external piping follows B31.1, together with the boiler code. The steam and condensate lines that run out to process users are often designed to B31.3 as part of the plant piping. The project decides where the change happens and marks it as a code break on the P&IDs and the line list.
Many offshore platforms have no steam system at all. They heat with hot water or a heating medium loop, which sits inside the B31.3 scope, so B31.1 seldom appears there.
Common confusions
B31.1 is a sister section to B31.3, not an older version of it. The two have different subjects, and each is revised on its own cycle.
Steam is only part of B31.1. The water, oil, gas and air services of a power plant fall under it as well, and B31.3 can also carry steam inside a process plant.
The equipment at either end is outside both sections. Pressure vessels follow ASME Section VIII, and the boiler itself follows BPVC Section I.
How the choice shows up on a project
Each piping class sheet names its design code. The line list carries the code for every line, and a code break symbol on the P&ID shows where it changes. Design, examination and test records then follow the section named for that line.
Questions
Is ASME B31.1 the same as B31.3?
No. B31.1 is the Power Piping section and B31.3 is the Process Piping section of the ASME B31 code. They share a numbering style and many ideas, but their allowable stresses, examination and testing rules differ.
Which code applies to steam piping in a refinery or gas plant?
Boiler external piping follows B31.1 together with BPVC Section I. Steam and condensate lines inside the process units are often designed to B31.3 as part of the plant piping. The owner sets the split and marks the code break on the drawings.
Can one line be designed to both B31.1 and B31.3?
In practice the project picks one section for each piping system. Where a system crosses from one to the other, the project draws a code break, and each side follows its own section.
Does ASME B31.3 cover boiler piping?
No. B31.3 excludes power boilers built to BPVC Section I and the boiler external piping that must meet B31.1. See ASME B31.3 for where the process piping code stops.
This page explains two standards in plain words. It is not a substitute for the standards themselves, and project specifications often add to both. Deck Twin uses these standards as reference values for visualisation. Check the current edition of each standard before using any value for design, procurement or fabrication.