ISO 11064
Ergonomic design of control centres
ISO 11064 is the control room design standard. A plain guide to its seven parts: layout, consoles, displays, lighting, noise and design checks.
Scope
ISO 11064 is the international standard for designing control rooms around the people who work in them. Its full title is Ergonomic design of control centres. It has seven parts, plus a technical report, ISO/TR 11064-10, that introduces the series.
It applies to any room where operators watch and run a process around the clock: process plants, power stations, pipelines, rail and road traffic, and emergency services. On oil and gas facilities it is used for central control rooms offshore and onshore, local equipment rooms with operator stations, and remote operations centres.
The standard is mostly a method, not a list of sizes. It tells the design team what to work out and in what order, starting from the operators' tasks. Part 5 gives general principles for displays, controls and alarms. On process plants the screen graphics are usually designed to ISA-101, and the alarm system is managed to ISA-18.2 or IEC 62682.
The seven parts of ISO 11064
Each part covers one layer of the design, from the whole building down to the screen. Most projects use all seven, in roughly this order.
| Part | First published | Title | What you use it for |
|---|---|---|---|
| ISO 11064-1 | 2000 | Principles for the design of control centres | The design process: five phases, from setting the goals to feedback after start-up |
| ISO 11064-2 | 2000 | Principles for the arrangement of control suites | The rooms around the control room, such as equipment rooms, offices and rest areas, and how people move between them |
| ISO 11064-3 | 1999 | Control room layout | Where the consoles, shared displays, doors, windows and walkways go |
| ISO 11064-4 | 2004 (second edition 2013) | Layout and dimensions of workstations | The console itself: desk height, reach, leg room and screen positions |
| ISO 11064-5 | 2008 | Displays and controls | How information, controls and alarms are presented to the operator |
| ISO 11064-6 | 2005 | Environmental requirements for control centres | Temperature, air quality, lighting, noise, vibration and interior finishes |
| ISO 11064-7 | 2006 | Principles for the evaluation of control centres | How to check the design, on paper and with operators, before it is built |
ISO reviews each part about every five years and may confirm or revise it. ISO lists Part 3 as due to be replaced by a revision now in development, ISO/AWI 11064-3. Check the ISO catalogue for the current edition before you buy or cite a part.
ISO 11064-1: how a control room is designed
Part 1 sets out the process. It has five phases, and operators take part in each one. The work loops back whenever a later phase shows that an earlier decision does not hold.
- 1
Clarify
Write down what the control room is for, who will work there, and the limits: budget, building, regulations and existing systems.
- 2
Analyse and define
List the functions and tasks. Decide what people do and what the system does, how many operators each shift needs, and what each job covers.
- 3
Conceptual design
Sketch the control suite, the room layout, the workstations, the displays and the environment. Compare a few options against the task list.
- 4
Detailed design
Turn the chosen concept into drawings and specifications. Test it with mock-ups, 3D models or walk-throughs, and fix what the operators find.
- 5
Operational feedback
After start-up, collect what works and what does not. Use it for changes to this room and for the next project.

ISO 11064-2: the rooms around the control room
Part 2 covers the control suite: the control room together with the rooms that support it. On a typical site these include an equipment room, an engineering or training room, offices, a meeting or permit area, a rest area, a kitchen and toilets.
The method starts from an analysis of the functions and tasks the suite must support. The team identifies the functional areas, estimates the space each one needs and works out the operational links between them, then draws preliminary layouts that keep the busiest links short.
In practice this usually means an operator can reach the rest area and the toilets without being away from the desk for long, and visitors and maintenance staff can reach the equipment room and the permit desk without walking through the control room.
ISO 11064-3: laying out the control room
Part 3 is the part most people mean when they search for the ISO 11064 control room standard. Its main rules are simple to state.
Seat operators who work together close to each other, so they can talk without leaving their console. Every operator who needs a shared display, such as a video wall, must be able to read it from a normal seated position. The supervisor should be able to see the operators and the shared displays from the supervisor desk.
Keep walkways behind the operators, not between them and the displays. Place the main doors where people coming in do not cross the operators' line of sight. Windows are welcome, but not behind the screens or directly in front of the operators, where they cause glare.
Leave space around consoles and system cabinets for maintenance, and leave room to add a workstation later. A raised floor and a suspended ceiling, as in the room shell, carry the cables, air and lighting.
ISO 11064-4: the console and workstation
Part 4 does not give one correct console size. It gives a way to work the size out from the people who will sit there, usually from the 5th percentile to the 95th percentile of the user population. A small operator must be able to reach the controls and see over the screens. A large operator must have enough leg room.
The console is designed mainly for seated work at screens, so the operator chair and the desk are designed together. The screens used most sit in front of the operator, at a comfortable viewing distance and slightly below eye level. Sit-stand desks are common in new rooms because they let each operator change posture during a twelve-hour shift.
ISO 11064-5: displays and controls
Part 5 covers how information reaches the operator and how the operator acts on it. It gives principles, requirements and recommendations for displays, controls and their interaction, in both hardware and software, on workstation screens and on shared displays. It also has high-level requirements for alarms.
It deals with choosing the right type of display or control, structuring and presenting information on screens, and setting up control and dialogue procedures. In plain terms, good practice is to show the operator what the task needs and no more, and to keep layouts, colours and words the same on every display. The state of the plant should be clear at a glance, and an alarm should stand out from normal information.
Part 5 is written for every kind of control centre and does not set a graphic style. On process plants the screens themselves are normally designed to ISA-101, and the alarm system to ISA-18.2 or IEC 62682.
ISO 11064-6: the room environment
Operators stay alert for long shifts only if the room is comfortable. Part 6 covers temperature, air, lighting, noise, vibration and interior finishes. The figures below are the ones quoted most often.
| Item | Commonly quoted value |
|---|---|
| Air temperature, winter | 20 to 24 °C |
| Air temperature, summer | 23 to 26 °C |
| Ambient noise | Not above 45 dB LAeq |
| Lighting | Dimmable and free of glare on the screens. The level is set for the tasks, such as screen work or reading paper. |
The temperature and noise values are widely quoted from the informative guidance in ISO 11064-6:2005. They are not a copy of the standard. Confirm them against the current edition and your local rules.
ISO 11064-7: checking the design
Part 7 covers evaluation of the control suite, the room, the workstations, the displays and controls and the environment. It is built around verification and validation. Verification asks whether the design meets its written requirements. Validation asks whether operators can do their real tasks with it.
Part 7 makes these checks part of the design process from the start. Early checks usually use drawings and checklists. Later ones often use walk-throughs with operators, full-size mock-ups of the console, 3D models of the room and simulator sessions. Findings are best closed out before the room is built, when a change is still cheap.
A 3D model is one of the ways to run these checks, and many control room projects build one. The control room example shows the kind of model used for a sightline and walkway review.
ISO 11064 on oil and gas facilities
Offshore, the central control room usually sits in the living quarters or in a protected module, away from the process. Onshore it is often in a blast-resistant building. In both cases the room is small and staffed day and night, so the layout matters more than in an office.
ISO 11064 is voluntary on its own. It becomes a requirement when a contract, a company specification or a regulator calls for it. In Norway the NORSOK standards on working environment refer to it. Projects often use it together with EEMUA 201 for control room design, ISA-101 for HMI screens, and EEMUA 191 or ISA-18.2 for alarms.
A short checklist
- 1
Tasks first
Is there a task analysis, and were operators involved in it?
- 2
Sightlines
Can every operator read the shared displays from the seat?
- 3
Communication
Do operators who work together sit within easy speaking distance?
- 4
Traffic
Do visitors and maintenance staff stay out of the operators' view?
- 5
Console fit
Does the console suit both the smallest and the largest expected user?
- 6
Environment
Are glare, noise, temperature and fresh air planned for a full shift?
- 7
Evaluation
Was the design tested with a mock-up or a 3D model before construction?
Key concepts
- Human-centred design
- The design starts from the operators' tasks, not from the equipment. Task analysis, operator input and iteration are part of the process from the start.
- Control suite
- The control room plus the rooms that support it: equipment rooms, offices, a kitchen, rest areas and toilets. Part 2 covers how they are arranged.
- Sightlines
- The line from an operator's eyes to a display. It must clear the console and the screens in front, so viewing distance and angle set the size and height of a shared display.
- User population
- The range of body sizes of the people expected to work in the room. Dimensions are worked out from this range, not from an average person.
- Verification and validation
- Verification checks the design against its written requirements. Validation checks that operators can do their tasks with it. Part 7 asks for both.
Questions
What is ISO 11064?
It is the international standard for the ergonomic design of control centres, in seven parts. It covers the design process, the rooms around the control room, the room layout, the workstations, the displays and controls, the environment and the evaluation of the result. It is used for control rooms in process plants, power, transport and emergency services.
How many parts does ISO 11064 have?
Seven. Parts 1 to 7 cover design principles, control suites, room layout, workstations, displays and controls, the environment and evaluation. ISO/TR 11064-10 is a technical report that introduces the series.
Is ISO 11064 mandatory?
No, not on its own. It is a voluntary standard. It becomes binding when a contract, a company specification or a regulator requires it, which is common on oil and gas, power and rail projects.
What does ISO 11064 require for a control room console?
Part 4 covers the workstation. The console is designed from the operator tasks and from the body sizes of the expected users, from small to large. It sets how to work out viewing distances and angles, reach zones, leg room and the sightline over the console to shared displays. It does not give one fixed console size, so a console is checked against the task analysis for that room. See the control console.
What is ISO 11064-1?
Part 1 gives the principles for designing a control centre and the process to follow. The work moves in phases: clarifying the goals, analysis and definition, conceptual design, detailed design and feedback from operation. Operators take part throughout.
What is ISO 11064-2?
Part 2 gives the principles for arranging the control suite: the control room and the rooms around it, such as equipment rooms, offices, rest areas and the routes between them. Rooms are placed from an analysis of the tasks and the operational links between areas.
What is ISO 11064-3?
Part 3 covers the layout of the control room itself: where the consoles, shared displays, doors, windows and walkways go, so that operators can see the displays and talk to each other.
What is ISO 11064-4?
Part 4 covers the layout and dimensions of workstations. It gives the method for sizing a console from the tasks and the body sizes of the users, including viewing distance, reach and leg room.
What is ISO 11064-5?
Part 5 covers displays and controls: how information, alarms and controls are presented to the operator. It does not set a graphic style, and on process plants the screen graphics are usually designed to ISA-101.
What is ISO 11064-6?
Part 6 covers the environment of the control centre: the thermal environment, air quality, lighting, acoustics, vibration and the look of interior finishes. Its guidance is the source of the comfort ranges usually quoted for control rooms.
What is ISO 11064-7?
Part 7 gives the principles for evaluating a control centre. Verification checks the design against its requirements. Validation checks that operators can do their tasks with it. The methods include walk-throughs, mock-ups and simulation, and they are used during the project, not only at the end.
What is the difference between ISO 11064 and ISA-101?
ISO 11064 covers the whole control centre: the design process, the layout, the consoles, the environment, and in Part 5 general principles for displays and controls. ISA-101 is written for process-industry HMIs: how process graphics are structured, coloured and navigated. A control room project normally uses both.
Where can I get ISO 11064?
Each part is sold separately by ISO and by national standards bodies such as BSI, DIN and ANSI. In Europe the parts are published as EN ISO 11064. This page explains the standard in plain words and is not a substitute for it.
In Deck Twin
The central control room example is a full room built from library components. The control console is set by segments, layout, segmentWidth, deskHeight, sitStand and monitor rows, so a curved or angled console can be laid out in front of a video wall. The room provides the raised access floor, suspended ceiling and doors for a control room shell. A 3D layout like this is useful for the sightline and walk-through checks in the detailed design phase. There is no lib/standards function for ISO 11064, and the layouts have not been through an ISO 11064 evaluation.
Deck Twin uses these standards as reference values for visualisation. Check the current edition of each standard before using any value for design, procurement or fabrication.